Oregon Street

  • Oregon St
  • D140 Oregon Street_11275 MI2

Lead Partner: New Gorbals Housing Association

Project Team: Page and Park, Architects: JM Architects; Quantity Surveyors: Neilson Binnie McKenzie; Structural Engineers: Clyde Design Partnership; Civil and Structural Engineers: RJA Consulting; Planning Supervisors: Carr McLean Watson. Main contractor Campbell Construction

Project History
Click an image to enlarge

  • High flats during demolition
  • Construction commences
  • Construction continues
  • Work nearing completion
  • Oregon Street is complete
  • Oregon Street is complete
  • Detail of Oregon Street buidling
  • Detail of Oregon Street buidling

Location:

Glasgow City Centre, Gorbals

Description:

This is a 2-phased project with a total of 104 housing units and one or two shops. The homes are being developed for rent and replace two multi-storey flats which were demolished in 2006. Although planned in two phases both phases have been constructed together and the entire project was completed in 2009 with an official opening in May 2009.

Current status:

Completed.

Timescale:

Completed May 2009.

Cost:

£13 million.