Rashielee South Sheltered Housing

  • Rashielee sheltered housing
  • Rashielee sheltered housing
  • New housing at Rashielee

Lead Partner: Horizon Housing Association

Other Partners: Bridgewater Housing Association

Project Team: Architects - Anderson Bell Christie Quantity Surveyor - Reid Assocates Engineers - Scott Bennett Associates, Planning Supervisor - Cmist Clerk of Works - Horizon Housing Assocation, Contractor - Cruden

Project History
Click an image to enlarge

  • Under construction
  • Under construction
  • Rashielee sheltered housing under construction
  • Rashielee sheltered housing under construction
  • Development at Rashielee nearing completion
  • Development at Rashielee nearing completion
  • Development at Rashielee nearing completion
  • Housing completed at Rashielee
  • Sheltered housing
  • Sheltered housing

Location:

Clydebank & Erskine, Erskine

Description:

This new build housing project is a joint development between Bridgewater Housing Association and Horizon Housing Association in partnership with Communities Scotland and Renfrewshire Council. The project provides 57 new homes for a range of clients in a variety of care settings and includes elderly amenity housing, supported frail elderly provision and wheelchair accessible housing.

Current status:

Completed

Timescale:

Phased handover from May 2007 through to December 2007.

Cost:

£6.6m